All windows in place
It's taken a while but all the oak window frames are now in place. There is still a bit of stonework to do around each frame to ensure that they are secure.
The roofer was expected this week but because of the bad weather they should be here at the start of next week. Fortunately they can start on the back putting in the veluxes. That should give me a little more time to finish the window frames and fit the roof timbers.
I've ordered the five windows for upstairs which should be available for collection in two weeks. Once the roofers have finished I can fit the windows and see some real progress.
| 8:47:11 AMTwo window frames installed.
Pictured right is the first window frame put into place. At the moment it is supported by scrap wood nailed and screwed to the floor and purlins inside. The silver metal brackets will 'bind' the frame into the stonework once it has been placed and built up around the frame. Positioning the frame was fairly tricky as they are heavy bits of wood and trying to juggle everything vertical and square took several attempts. I'm really glad I decided to use oak pegs on the joints for ease of assembly and dis-assembly!
The window is slightly larger than the original window, you can just see the original roofline behind. The extra height means you can see out of the window from the room without bending down, just. Planning restrictions meant I was limited to similar proportions to the old opening and three-quarters of the window had to be below the soffit. This was part of the reason for putting in new window sills, to raise the height, and retain the window proportions.
A second window frame in place with some stonework mortared into place. The stone is really only a facing as I will shutter up the rear of the frame and concrete the whole lot in to make sure it's secure.
The guttering will be removed by the roofing company when they come and replace the roof later this week. I will have to construct the woodwork from the top of the frame back to the roof once the roofers remove the old roof.
One minor disappointment was that last night it rained heavily and a brown stain leeched out of the oak and ran down onto the window sill staining the edges. Not something I had anticipated, so for now I've put a couple of pieces of slate over the sill to try to prevent further staining.
| 7:42:49 PMRenovation tax
Bah, got an unexpected bill today for 400 euro for renovation tax !!
Two pages of explanatory notes and I'm still not much wiser what it's for. It's obviously triggered by the permis de construire (planning permission) and the price is based on the surface area of the construction or renovation.
Fortunately it's not payable until January 2009, yeah, like I'm going to remember to pay a bill in 18 months time.
| 8:15:56 PMWindow frames
Work
has started
on the window frames this week. At the moment I've just got some large
holes in the wall upstairs ready for the dormer windows. All the window
sills have been fitted and the idea is that the window frames I am
making will sit on the sill and then the stonework can be rebuilt back
upto the frame. The window is the fixed to the inside of the frame.
Most of the houses in this area of Brittany use granite sets to frame the windows and doors. It looks great but would get very expensive in my case because I would want to add granite to every door and window. The other alternative is just to use the existing stone to form the window opening, but it's very time consuming and difficult to form a square edge with the stone I have on site. The compromise I have come up with is to use local oak beams to create the window opening then rebuild the stone us to the edge of the frame.
I bought eight lengths of 3m x 100mm x 200mm oak beams and this is what I am using to create the window frames.
Each of the windows to be fitted are 80cm wide by 135cm tall and will be fixed to the inside of the frame. French windows all open inwards so the actual window is about 5cm wider and 4cm taller to overlap my oak frames.
Hopefully this will become clearer once they are in-situ.
The sections shown above are 145cm long with the top section 100cm. Once they are assembled with a simple joint it leaves the correct size opening. Each of the top corners will be drilled and pegged. I expect to use about a 15mm hole then fashion the pegs from some of the oak offcuts.
At the moment each frame is taking about 2-3 hours to make because none of my tools are quite big enough to handle the wood. All the joints and chiselling are being done by hand.
One frame done, just another four to go !
| 8:15:17 PM
Another door and two windows finished.
Whilst I've been working on the right hand side door and window I have also been progressing with the left hand door and window. The process has been very similar. I wanted to replace the old concrete lintel because it did not look safe as bits of concrete were crumbling and you could see old rusty pieces of ironwork had 'blown' the concrete. Also the door was very low, 190cm, and this was a good opportunity to raise the door height to a more standard 200cm.
I'm not terribly keen on the red brick, but having had the experience of rebuilding stonework I have decided to leave it alone. It's just too large a job. Most of it will be covered up by window shutters anyhow.
So, all my five upstairs windows now have new window sills at the correct height for the floor and are ready for the new oak window frames.
That's next weeks job, before the roofer comes, to build the window frames.

|
4:01:13 PM Door and window completed
| 8:50:40 PMSeptic tank and well location
A while ago I got my permit for the septic tanks based on the soil study performed back in May. Before the study we had a meeting at the DDE (planning office) and one of the options I asked about was selling the bottom of the 80 meter long garden for a building plot. The DDE said that the bottom parcel of land was designated agricultural and I would never get planning permission for it. Because I couldn't build on the land I took the option to site the septic tank soakways down the bottom of the garden and because of the slope it meant I didn't need a pump. The garden rises very slightly before falling away. I wasn't that keen on the extra expense of two pumps and the potential for failure. I also knew from having a previous spetic tank installation that the soakaway had to be at least 35 meters away from a well. My well is fairly close to the house. So based on the lie of the land and the location of the well the soakaways ended up nearly 60 meters from the house.
Since then I have spoken to several friends who remarked that it seemed a shame to 'waste' the bottom of the garden and actually the pumps aren't that expensive and rarely break down. The company that came to give me a quote for the septic tank installation also mentioned that having the soakaways so far away did leave the potential for any blockage in the long pipe runs. However like me he agreed that the 35m restriction with the well did limit my options.
Fortunately I bumped into someone the other day that builds houses in France and they mentioned that they managed to get planning permission on agricultural land, but it did take loads of applications and several years. Because of it's potential value I shouldn't give up. Just keep trying.
Obviously I couldn't do anything with the land with two soakways buried just beneath the surface so Debbie phoned the SPANC (Service Public d'Assainissment Non Collectif) to see if there were any options to get around the 35m well restriction. The good news is that they have sent me a form to sign and return in which I have to declare that I will never use the well for drinking water, only for watering the garden, and then I can put the soakaways closer to the house so freeing up the bottom of the garden. Along with the form I need to return a modified plan showing the new location of the soakaways and new pumps.
Result.
| 7:49:53 PMSome progress on the new openings
| 3:35:06 PM







